Shingletown Phase 2 Fuelbreaks (SHU)

Shingletown Phase 2 Fuelbreaks (SHU) - #134
Grantor: CALFIRE
Awarded*: $949,473.25
Activities: Signed agreement 1/20/2026. HWY 44 Maintenance deliverables completed on 450 acres. MOU executed for thinning and chipping larger fuel concentrations on HWY 44 fuelbreak.
Remaining Treatment Funds*: $800,000
Status: CEQA complete. Permits completed. Hwy 44 maintenance completed. RFPs for RFP for mastication in September/October 2026. WSRCD MOU Fuelbreak work October 2026.
 Exp Date: 3/15/2029

* Does not include proprietary cost match information