North Susanville WUI Fuels Treatments

North Susanville WUI Fuels Treatments - #103
Grantor: CALFIRE
Awarded*: $2,999,924.32
Activities: CEQA cleared. Landowner agreements complete. Biomass 100% complete. Mastication 60% complete.
Remaining Treatment Funds*: $1,400,000
Status: Mastication active on Eagle Lake Road. Acres added to widen Fuelbreak. Arch surveys and hand thinning scheduled for spring 2026. Hazard tree assessments ongoing. RFP for hazard tree pushed to after mastication completed. CALFIRE Rx Burn on areas LFSC prepped.
Exp Date: 3/15/2030

Does not include proprietary cost match information